The data center market is moving faster than the headlines, and we see it in our inbox every week.
The gap between what buyers ask for and what can actually be energized is where deals are won or lost. Speed to Power is our weekly read on that gap: what changed, why it matters and what to do next. It's short, Midwest-first and nonpartisan. Counts as of Nov. 9, 2026.
1. Riot-Anthropic sets a $130/kW-month marker. Riot's 10-Q discloses an Anthropic lease for an expected 910 MW at Corsicana, Texas, phased mid-2027 to July 2028, starting at $130/kW-month with 3% annual bumps over about 15 years.
What it means: Expect owners to quote this and buyers to discount it. It's a 910 MW, 15-year Texas deal with a frontier-lab tenant. For Midwest powered land and colo, the gap from $130 comes down to two questions: when are the MW energized, and how long is the term? Riot 10-Q
2. Local voters limited data centers in 40 of 41 ballot measures. On Nov. 3, voters favored limiting data center development in 40 of 41 local measures. The only exception cited was Harwood, N.D.
What it means: Community risk now gets underwritten like power. Before you check the substation for a KS or MO site, check the city's agenda and ballot calendar. Source
3. Three Kansas cities approved bans. Voters in El Dorado, Emporia and Ottawa approved bans or moratoria on larger data centers, with thresholds around 10 MW of load and, in Emporia, a water-use cap.
What it means: 10 MW is now a live local line in parts of Kansas, and 22 of the 75 requirements we're tracking sit at or under it. Read the ordinance text before you market or underwrite any Kansas site. Source | Source
4. Evergy's large-load book keeps growing. Evergy announced about 250 MW of ESA amendments (110 MW binding, 140 MW contingent on an SPP transmission study) and an LOI with Digital Realty for a 1.4 GW Kansas expansion next to an existing 600 MW project.
What it means: Signed load in Evergy territory is real, but expansion MW still wait on SPP studies. On any KC-area site, ask whether the MW are binding or study-contingent, because that answer sets your timeline. Source | Source
5. Ameren named Google and Amazon inside 2.8 GW of signed Missouri deals. On its Nov. 6 call, Ameren said Google and Amazon are inside 2.8 GW of signed Missouri service agreements, with more load under construction agreements and in interconnection studies.
What it means: In Ameren's Missouri territory, the hyperscalers are already in line. For everyone else, a will-serve letter or study result is worth more than acreage. Price a site without one as unknown power. Source | Source
Have a site, a requirement or equipment to place? Use the short form and Mitch will follow up. City and county are enough to start, so leave out street addresses and confidential files. Submitting the form doesn't sign you up for marketing.
Next up: 25 MW is the new line. What the Nov. 3 local votes mean for site size and phasing.
Know someone chasing power, sites or capacity in the Midwest? Forward this. It takes 10 seconds and it's the best way to help them.
Hit reply and tell us one thing you're seeing in the market. We read every one, and the best ones (anonymized) end up here.
Talk soon,
Logan Freeman, Midwest CRE Advisors