$130/kW-month, 40 of 41, and ~5 GW on our desk

November 14, 2026

Why we're starting this

The data center market is moving faster than the headlines, and we see it in our inbox every week.

  • 75 requirements, ~5 GW. 75 data center requirements with a stated size have come to us. Together they total nearly 5 GW, and that's the low end of what each one asked for.
  • 3 GW+ in six weeks. 54 of them, more than 3 GW, have been live with us since Oct. 1.
  • 386 sites. On the supply side, we're tracking 386 potential sites and capacity sources, we've screened 146 sites against nearby substations, and we're working about 145 with an owner, co-broker, partner or operator.

The gap between what buyers ask for and what can actually be energized is where deals are won or lost. Speed to Power is our weekly read on that gap: what changed, why it matters and what to do next. It's short, Midwest-first and nonpartisan. Counts as of Nov. 9, 2026.

What we're seeing from our seat

  • Smaller than you'd think. Half the sized requirements (38 of 75) are under 25 MW, and 22 are 10 MW or less. The gigawatt campuses get the headlines, but most of the volume is in the 5 to 25 MW range.
  • "Now" is the most common timeline. About 1 in 3 (26 of 75) want power now or by Q1 2027. At least one told us it would sign within two weeks if the capacity fit.
  • Location is flexible. The power date isn't. 22 of 75 told us any U.S. market works. They'll go where the power is.
  • Half come through someone else. 39 of 75 reached us through a broker, adviser or other intermediary. The end user is rarely the first call, so we verify who's real before we spend anyone's time.
  • Liquid is the default. Of the 20 requirements that named a cooling approach, 15 mentioned liquid. Every one that gave us a rack density was planning for 100 kW+ racks at peak.

Market Pulse: Top Stories This Week

1. Riot-Anthropic sets a $130/kW-month marker. Riot's 10-Q discloses an Anthropic lease for an expected 910 MW at Corsicana, Texas, phased mid-2027 to July 2028, starting at $130/kW-month with 3% annual bumps over about 15 years.

What it means: Expect owners to quote this and buyers to discount it. It's a 910 MW, 15-year Texas deal with a frontier-lab tenant. For Midwest powered land and colo, the gap from $130 comes down to two questions: when are the MW energized, and how long is the term? Riot 10-Q

2. Local voters limited data centers in 40 of 41 ballot measures. On Nov. 3, voters favored limiting data center development in 40 of 41 local measures. The only exception cited was Harwood, N.D.

What it means: Community risk now gets underwritten like power. Before you check the substation for a KS or MO site, check the city's agenda and ballot calendar. Source

3. Three Kansas cities approved bans. Voters in El Dorado, Emporia and Ottawa approved bans or moratoria on larger data centers, with thresholds around 10 MW of load and, in Emporia, a water-use cap.

What it means: 10 MW is now a live local line in parts of Kansas, and 22 of the 75 requirements we're tracking sit at or under it. Read the ordinance text before you market or underwrite any Kansas site. Source | Source

4. Evergy's large-load book keeps growing. Evergy announced about 250 MW of ESA amendments (110 MW binding, 140 MW contingent on an SPP transmission study) and an LOI with Digital Realty for a 1.4 GW Kansas expansion next to an existing 600 MW project.

What it means: Signed load in Evergy territory is real, but expansion MW still wait on SPP studies. On any KC-area site, ask whether the MW are binding or study-contingent, because that answer sets your timeline. Source | Source

5. Ameren named Google and Amazon inside 2.8 GW of signed Missouri deals. On its Nov. 6 call, Ameren said Google and Amazon are inside 2.8 GW of signed Missouri service agreements, with more load under construction agreements and in interconnection studies.

What it means: In Ameren's Missouri territory, the hyperscalers are already in line. For everyone else, a will-serve letter or study result is worth more than acreage. Price a site without one as unknown power. Source | Source

Checklist you can reuse

  1. Is a moratorium or pause proposed or in force here? Through what date, and what does it cover?
  2. Which utility and which published rate schedule serve this site? Is the schedule approved or still proposed?
  3. Is the MW claim documented (agreement or will-serve letter) or only marketed?
  4. Is a transmission or large-load study still open that could change timing?
  5. Could a local vote, petition, recall or public hearing affect rezoning, incentives or the project itself?

Have a site, a requirement or equipment to place? Use the short form and Mitch will follow up. City and county are enough to start, so leave out street addresses and confidential files. Submitting the form doesn't sign you up for marketing.

Share a site or requirement

Next up: 25 MW is the new line. What the Nov. 3 local votes mean for site size and phasing.

Know someone chasing power, sites or capacity in the Midwest? Forward this. It takes 10 seconds and it's the best way to help them.

Hit reply and tell us one thing you're seeing in the market. We read every one, and the best ones (anonymized) end up here.

Subscribe to Speed to Power

Talk soon,

Logan Freeman, Midwest CRE Advisors