25 MW is the new line

November 18, 2026

What voters decided close to home

  • Kansas, Ottawa. Voters approved a ban on data centers designed to use 25 MW or more, with about 72% voting yes (2,882 to 1,129 in the reported count; Franklin County canvassed Nov. 16). Because it came in by citizen petition, Kansas law keeps the city commission from changing it for 10 years. Only voters can.
  • Kansas, El Dorado. Voters approved a 10-year ban on "high-impact" data centers, defined as a peak electrical load exceeding 10 MW or a daily water draw exceeding 100,000 gallons, and on certain battery storage systems, with about 71.5% voting yes. The city says the ban covers land inside city limits, not its three-mile extraterritorial zoning area, though the commission may take that up.
  • Kansas, Emporia. Voters approved a ban on high-impact data centers, including facilities with a peak load of 10 MW or daily water use above 10,000 gallons, 4,346 to 2,891 (60.1%). A separate battery storage ban also passed. Lyon County certified the results on Nov. 12 with no change. The city says the ordinance cannot be enforced until a judge rules on whether the petition is legal under Kansas law, so read the status before you underwrite an Emporia site.
  • Kansas, Americus. Voters approved restrictions on data centers, with about 68% voting yes.
  • Illinois, Metro East. Advisory questions on permitting new data centers lost by about 3 to 1 or more in Granite City Township (74.4% against), Nameoki (77.9%), Venice (75.9%), and Chouteau (83.3%). In Will County, Joliet Township voted 78.9% against in an advisory vote, after the city council had already approved a campus there.
  • Ohio, Ashville. Voters rejected the village's agreement for a campus that was already under construction, with about 82% against.

Why 25 MW keeps showing up

At least nine measures drew the line at 25 MW: Ottawa, plus Conneaut, Defiance, Granville, Oregon, Pataskala, Piqua, Sunbury, and Trenton in Ohio. A few drew it lower. Grove City, Ohio, now requires a citywide vote for projects that draw more than 20 MW at peak, use 50 or more acres, or use more than 500,000 gallons of water a day (Franklin County certifies Nov. 20). Sabattus, Maine, passed a 180-day moratorium on data centers of 20 MW or 10,000 square feet and up. Urbana, Ohio, banned data centers larger than 7.5 MW. Many others banned data centers outright or sent them to a public vote. And the next one on the calendar, Mandan, N.D., on Dec. 15, would cap data centers at 25 MW of combined demand.

So here is a working rule. In many communities, a facility under 25 MW is still treated like an industrial user. Above that, the project becomes a political process. In parts of Kansas, the live local line is lower, at about 10 MW.

It is not the only line on the map. In Kansas, the large-load rate plan the KCC approved in 2025 applies to new loads of 75 MW or more. A site can clear the local cap and still face a different set of utility terms as it grows.

And the state layer moved after Nov. 3. Kansas Governor-elect Cindy Holscher campaigned on a moratorium that would pause data center approvals until the state sets guardrails. Nothing is enacted, and the threshold and timing are unknown until the 2027 session, but Kansas sites now need a state policy check as well as a local one. The state canvass board certifies final results on Dec. 1.

From our seat

In Volume 1 we noted that half of the sized requirements on our desk (38 of 75) are under 25 MW, and 22 are 10 MW or less. That is why these local lines are not a side issue. They sit right in the middle of the deals we actually see.

What readers asked after Volume 1

We read the replies. Here are two, anonymized.

Q. Can you work a 1 GW or larger requirement?

A. Yes. We see a few of those. Most of the live volume is still under 25 MW, but the large ones are real. The first filters are the same: when do you need the power, is the MW claim documented, and does a local vote or ordinance cap the site?

Q. We have powered sites in other states and want to look at the Midwest. Is that a conversation worth having?

A. Yes. Reply with the state, whether the land is vacant or already improved, and whether the power is documented or still in study. City and county are enough to start.

Market Pulse

Five items from the past week worth knowing if you own, buy, or are siting Midwest land.

  1. Edgerton, Kan., will vote in March. On Nov. 12 the city council sent a citizen petition banning high-impact data centers (over 10 MW of peak demand or 100,000 gallons of water a day) to a March 2027 special election, along with a battery storage ban. Why it matters: the 10 MW petition model has reached the Kansas City metro, so Kansas-side metro sites need a ballot check, too. (City of Edgerton, Olathe Today)
  2. Jackson County, Mo., is writing its rules. The county's 180-day moratorium on data center and battery storage applications is expected to expire in December, and a resolution introduced Nov. 9 sets guiding principles for small, mid-size, and hyperscale data centers before then. Why it matters: on the Missouri side of the metro, check the county code, not just city zoning, and expect different standards by facility size. (Jackson County Legislature, Res. 22450)
  3. Nebraska public power adds a large-load rate. NPPD's board approved a new large-load rate on Nov. 13, meant to minimize cost shifts and protect existing customers if a large load leaves, alongside 2027 rate increases. Why it matters: large-load terms are now standard at investor-owned and public power utilities alike, so budget for minimum bills and exit protections in every Midwest utility conversation. (NPPD)
  4. Grid operators filed their large-load rules at FERC. MISO, PJM, and others filed on Nov. 16, and SPP is due by Fri., Nov. 20. MISO's package includes a large load project review, new transmission service options, cost recovery agreements, and a separate service for loads that can cut use when the grid is tight. Why it matters: faster power increasingly means flexible or non-firm service, so a site's value depends on whether a user can live with curtailment or bring its own backup. (Utility Dive)
  5. Lenders want proof of power. The new CREFC Data Center Primer (2nd ed.) reports all-in ABS funding costs up more than 100 basis points since January, and its lender checklist asks early how much capacity is available now and what remains to be delivered. Why it matters: will-serve letters, study results, and a delivery schedule are now part of what makes land financeable. (CREFC)

What it means for owners, buyers, and operators

  1. Add a local ballot check to every site screen. Has a petition been filed? Is a charter amendment or referendum possible? Has the council faced a recall? When is the next local election?
  2. Size and phase to the line that actually applies. Do not assume 25 MW. In some Kansas cities the high-impact line is about 10 MW. Edge and inference deployments in the 5 to 25 MW range still fit under many of the new caps, but only if you read the ordinance.
  3. Price approved, powered sites accordingly. When new approvals slow down, sites that already have zoning, a utility path, and no ballot fight get scarcer.
  4. Watch the calendar. Nov. 20: Grove City certification and SPP's FERC filing. Nov. 24: Ohio certification deadline. Dec. 1: Kansas state canvass and Clarksville, Ark., votes. Dec. 8: Hollis, Maine, votes. Dec. 15: Mandan, N.D., votes on a 25 MW cap. December: Jackson County, Mo., moratorium expected to expire. March 2027: Edgerton, Kan., votes.

Checklist you can reuse

  1. What does the ordinance actually cap: MW, water, battery storage, or all data centers?
  2. Is the measure binding, advisory, or still in court?
  3. Does the cap apply to the whole campus, including later phases, and does it reach past city limits?
  4. Is a transmission or large-load study still open that could change timing, and is the service firm or curtailable?
  5. Could a local vote, petition, recall, or public hearing still affect rezoning, incentives, or the project itself?

Have a site, a requirement, or equipment to place? Use the short form and Mitch will follow up. City and county are enough to start, so leave out street addresses and confidential files. Submitting the form does not sign you up for marketing.

Share a site or requirement

Next up, next Tuesday: Volume 3, How to tell documented power from a marketed MW claim. Binding MW vs. study-contingent, and what to ask for in a utility letter.

Know someone chasing power, sites, or capacity in the Midwest? Forward this. It takes 10 seconds and it is the best way to help them.

Hit reply and tell us one thing you're seeing in the market. We read every one, and the best ones (anonymized) end up here.

Forwarded this email? Get Speed to Power every week: Subscribe to Speed to Power

Talk soon,

Logan Freeman, Midwest CRE Advisors

Sources

‍

VIEW FULL ARTICLEDOWNLOAD PDF