
Hi, it's Logan.
In Volume 1 I flagged the Evergy headlines: more signed load, a 1.4 GW letter of intent with Digital Realty, and a 140 MW expansion still waiting on a transmission study. Last Friday's special walked through how Ameren's queue actually works.
This is the deeper Evergy read. Not just what was announced, but how a large load gets in line, how the year-by-year ramp lines up against new plants, and what I'd ask before you price land or underwrite a site in Kansas or Missouri.
The ramp. Signed large-customer demand, which excludes the Digital Realty letter of intent and the contingent 140 MW, goes from about 350 to 400 MW in 2026 to about 750 to 850 MW in 2027, 1,300 to 1,400 MW in 2028, 1,800 to 1,900 MW in 2029, and 2,150 to 2,350 MW in 2030, then about 3,100 MW at peak after 2030. Using the midpoint of the 2026 band, that is roughly 6x by 2030 (our calc: 2,250 MW divided by 375 MW).
The contracted book. As of September 30, Evergy reported $8.9 billion of remaining contractual minimums on these large-load agreements, with a weighted average term of about 15 years. Those minimums typically equal 80% of expected annual capacity demand.
The clock vs new supply. This is the part the chart is for. Evergy's slides show about 5.1 GW of new nameplate through 2032 (about 3.7 GW of gas, 774 MW of solar, and 559 MW of batteries). Cumulative new nameplate is only 165 MW in 2027 and 465 MW in 2028, almost all solar, before the larger gas additions begin in 2029. Against the midpoints of the signed ramp, that is about 1,350 MW of signed load in 2028 vs 465 MW of new nameplate. On a nameplate basis the two series roughly meet in 2029, and by 2030 new nameplate is ahead of the signed book. That is our read of Evergy's slides, not Evergy's words. The dashed and dotted lines are our estimates, not Evergy guidance. Evergy gives no year-by-year timing for its pipeline, so we spread the Digital Realty letter of intent and the rest of Tier 1 evenly over 2029 to 2033, and Tier 2 over 2031 to 2035. Add only the letter of intent and the 140 MW, and new supply stays ahead after 2029. Add the Tier 1 and Tier 2 midpoints, and demand roughly matches new supply in 2030 and 2031, then passes it by 2032 (about 5,500 MW vs 5,053 MW). In other words, the plants on Evergy's slides cover the signed book, and the pipeline uses up that cushion within a few years. Nameplate is not accredited capacity, and the existing fleet and the SPP market also serve load. Evergy did not disclose a reserve margin. It did say that load beyond the 3.1 GW already signed will require incremental resources.
The Digital Realty letter of intent. The CFO said the ramp likely starts in 2029, picks up in 2030, and builds through 2033. Evergy expects to own most of the generation behind it, about $4 billion of capital for this project alone, and none of it is in the current five-year plan. The ESA is expected to be signed under the new Kansas tariff.
Capex and load. Capex through 2030 is now $22.5 billion, a $21.6 billion plan plus about $1 billion from the 2026 IRP, with a full update on the February call. The CFO's rule of thumb: about $3 billion of capex for every GW of new customer load. Weather-normalized retail demand rose 4.5% in Q3, with commercial up 8.7% on data center usage. Evergy still forecasts 7% to 8% annual retail load growth through 2030.
New plants. The 10-Q names Buchanan Bluffs Units 1 and 2, about 710 MW of gas each in Buchanan County, Missouri, targeted for 2031 and 2032. Mullin Creek 2, a 440 MW unit, has a settlement filed, with an order expected by January 2027. The plants have their own local process, too. On Nov. 16, the Missouri PSC held a public hearing in St. Joseph on the Buchanan Bluffs application, where residents raised water, air quality, and bill concerns. Evidentiary hearings in that case begin Feb. 24, and Evergy has asked for an order by April 2027.
The pipeline. Tier 1 expansions of 2.0 to 2.5 GW, now including the Digital Realty letter of intent and the contingent 140 MW. Tier 2 advanced discussions of 1 to 2 GW, mostly beyond 2030, with land or land rights and financial commitments already in place. Behind that, Evergy describes a much larger set of inquiries, well over 10 GW, that is not in the active queue. It says it will prioritize the best-fit projects as capacity opens. Management still has a high level of confidence in 5 to 7 GW of total large-load agreements, and it pointed to a steady cadence of conversions over the next 12 to 18 months.
This is the part I'd read twice, because it is where land value gets made or lost.
Evergy's Path to Power process, as set out in its Missouri rules for service to loads greater than 25 MW and in the Kansas large-load settlement, is the on-ramp. The large-load tariff is a separate gate, at 75 MW.
The 140 MW amendment signed in early November is a reminder that even an expansion of an already signed project can still be gated by a transmission study.
Kansas. The October 29 filing, the Customer Affordability Enhancement Plan, would create a new large-load vintage for newly signed customers: a cost rider tied to higher-cost new generation, plus nonrefundable advance payments. Evergy asked for expedited treatment and a February 2027 order. On the call, management pointed to midyear 2027. On Nov. 10, the KCC suspended the filing until June 28, 2027, which lines up with that midyear target, and let the state consumer advocate (CURB) intervene. The Digital Realty ESA is expected to move in tandem with that approval. A separate October 30 settlement would allow voluntary prepayments under the existing tariff, with a decision expected in the coming months.
Missouri. After the Digital Realty letter of intent, Evergy said the majority of the remaining Tier 1 expansion opportunities and Tier 2 advanced discussions are on the Missouri side. The Missouri Metro rate case includes a large-load stipulation with about a $60 million revenue offset, with an order expected in December and new rates in January 2027. The Missouri West case, filed November 3, includes about a $61 million large-load offset, with new rates expected in October 2027.
Same process family, different calendar, and a tighter ticket if you are signing a new Kansas large-load deal.
For landowners. Price your land by its stage, not its acreage. Raw land, a Path to Power request, a completed study, construction agreements, and an ESA with a creditworthy user are different assets. A buyer who has to post nonrefundable advance payments will underwrite your land with that cost in mind. Before you market on a study, ask Evergy whether it transfers to a buyer. That isn't public.
For developers. The big moves in Evergy's Nov. 5 update were amendments and a letter of intent at sites that already had land, local support, and a signed contract. That is the template. File the formal Path to Power request once you have site control, a defined point of interconnection, and a load profile, and can move on construction agreements when the study comes back. Filing earlier mostly buys a queue date with a shelf life. And if the campus will ever pass 75 MW, plan on the large-load tariff from day one, including the proposed Kansas enhancement if the site is on that side of the state line.
For users. The near-term plants are sized around load that has already signed. If you are not in that book yet, my read is that firm Evergy power for a new large load is more of a late-2020s to early-2030s conversation. The faster path is an expansion at a signed campus, and even that can wait on a transmission study. Bring your credit story early. Collateral is already two years of minimum bills, and in Kansas the next wave may also be asked for nonrefundable advances.
For everyone. Local support is part of Evergy's own screen. Management said new large customers are not a good fit in every community, and priority goes to areas backed by local permits and local support.
If you own land in Evergy territory, are building here, or need power in Kansas or Missouri in the next five years, I'd like to compare notes. City and county are enough to start, so leave out street addresses and confidential files.
I'll keep watching the Kansas tariff docket (now on a June 28, 2027 clock), the year-end transmission study on that 140 MW, the Buchanan Bluffs case, and Evergy's February update on the capital plan. What changed in your underwriting after this call? Hit reply. I read every one.
Talk soon,
Logan Freeman, Midwest CRE Advisors
Copyright 2026, Midwest CRE Advisors