Hi, it's Logan.
Quick note before we dig in: we'll be at the KC Tech Council's Energy & Data Center Innovation Summit today at Sporting Park in Kansas City, Kansas. We're hoping to meet more of the people working on power and data centers in our region, so if you'll be there, reply to this email and let's find each other.
A lot more of my week is spent in St. Louis these days, and every conversation there lands on the same question we hear in Kansas City: when will the power be there, what will it cost, and who is ahead of me in line?
Ameren answered more of that on its Nov. 6 call than it ever has. It raised its five-year plan, put new numbers on data center load, and laid out its pipeline stage by stage. Here's what it said, and how I'd use it.
Bottom line: Ameren is building new supply in step with its 2.8 GW of signed data center load, with about 3 GW of new nameplate landing in 2027 and 2028. That capacity is spoken for. The next 5.6 GW of firmed interest needs new agreements and resources that mostly arrive around 2032 to 2036.
Capital. A $38.1 billion plan for 2027 to 2031, up more than 20% from the prior five-year plan, with rate base growing about 13.3% a year. The 10-year pipeline is now more than $90 billion through 2036, up $19 billion, mostly to serve about 5 GW of Missouri load growth.
Generation. About 7.7 GW of new generation is planned from 2027 to 2031, roughly an 80% increase in Ameren Missouri's installed capacity, and about 5.3 GW of that is already announced as specific projects. The near-term pieces: the 800 MW Castle Bluff gas plant in 2027, the 800 MW Big Hollow gas plant and 400 MW of batteries in 2028, and the 2.1 GW West Alton plant targeted for 2031. Ameren's resource plan is built to serve 3.4 GW of additional demand by 2031 and 5 GW by 2036.
The next wave. Asked about customer deposits for future deals, management said "those types of arrangements are certainly on the table" for the next phase. Nothing has been filed yet.
This is the part I'd read twice, because it is where land value gets made or lost.
And the line is long. In testimony this May, Ameren said it had received additional transmission study requests representing about 15.5 GW of new load, on top of what was already signed or under construction agreement.
Ameren Illinois owns wires, not power plants, so supply comes from the market. Its proposed large-load rules, still pending at the Illinois Commerce Commission, would apply above 100 MW and rank the queue by what you can document: site control plus a named end user plus a supply plan goes first. Site control alone goes last. Ameren Illinois reported 850 MW of construction agreements as of the first quarter.
For landowners. Price your land by its stage, not its acreage. Raw land, a queued study request, a completed study, a signed construction agreement and an ESA with a creditworthy user are five very different assets. The real step up is the construction agreement. Before you market on a study, ask Ameren whether it transfers to a buyer. That isn't public.
For developers. File the formal study once you have site control, a defined point of interconnection and a load profile, and can fund a construction agreement within six months of results. Filing earlier mostly buys a queue date with a shelf life. And if the campus will ever pass 75 MW, plan on the large-load tariff from day one. Phasing under the line only works for genuinely small sites.
For users. The new plants are sized for load that has already signed. If you are not in the queue yet, my read is that firm Ameren power for a new large load is more of a 2032 to 2036 conversation. The near-term wins are expansions at signed campuses and the land around them. Bring your credit story early; collateral discounts run on ratings and liquidity.
For everyone. Zoning certainty is worth as much as power position here. The City of St. Charles has permanently banned large data centers, and Troy, Ill., has a moratorium with a 30 MW cap proposed. County versus city lines matter.
If you own land in Ameren territory, are building there, or need power in Missouri or Metro East in the next five years, I'd like to compare notes. City and county are enough to start, so leave out street addresses and confidential files.
What changed in your underwriting after this call? Hit reply. I read every one.
Talk soon,
Logan Freeman, Midwest CRE Advisors