What Ameren's Q3 Call Means for Powered Land in Missouri

November 13, 2026
Ameren Missouri large-load pipeline by stage, Q3 2026

Hi, it's Logan.

Quick note before we dig in: we'll be at the KC Tech Council's Energy & Data Center Innovation Summit today at Sporting Park in Kansas City, Kansas. We're hoping to meet more of the people working on power and data centers in our region, so if you'll be there, reply to this email and let's find each other.

A lot more of my week is spent in St. Louis these days, and every conversation there lands on the same question we hear in Kansas City: when will the power be there, what will it cost, and who is ahead of me in line?

Ameren answered more of that on its Nov. 6 call than it ever has. It raised its five-year plan, put new numbers on data center load, and laid out its pipeline stage by stage. Here's what it said, and how I'd use it.

Bottom line: Ameren is building new supply in step with its 2.8 GW of signed data center load, with about 3 GW of new nameplate landing in 2027 and 2028. That capacity is spoken for. The next 5.6 GW of firmed interest needs new agreements and resources that mostly arrive around 2032 to 2036.

What Ameren said

  • 2.8 GW of signed electric service agreements (ESAs) in Missouri. Google and Amazon are part of that book, with a combined $25 billion of planned investment in Montgomery County.
  • 5.6 GW more behind it: 1.2 GW of projects with construction agreements and 4.4 GW with completed interconnection studies. About 600 MW moved from study to construction agreement this quarter.
  • The clock: Ameren says it serves essentially no large loads today. Sales from the signed book begin modestly in late 2027, ramp mostly in 2028 and 2029, and reach full capacity in 2030.
  • Missouri sales growth of 12.9% a year from 2027 to 2031, built on 2.9 GW of new load by 2031. In February the plan assumed 1.2 GW by 2030.

The numbers behind it

Capital. A $38.1 billion plan for 2027 to 2031, up more than 20% from the prior five-year plan, with rate base growing about 13.3% a year. The 10-year pipeline is now more than $90 billion through 2036, up $19 billion, mostly to serve about 5 GW of Missouri load growth.

Generation. About 7.7 GW of new generation is planned from 2027 to 2031, roughly an 80% increase in Ameren Missouri's installed capacity, and about 5.3 GW of that is already announced as specific projects. The near-term pieces: the 800 MW Castle Bluff gas plant in 2027, the 800 MW Big Hollow gas plant and 400 MW of batteries in 2028, and the 2.1 GW West Alton plant targeted for 2031. Ameren's resource plan is built to serve 3.4 GW of additional demand by 2031 and 5 GW by 2036.

The next wave. Asked about customer deposits for future deals, management said "those types of arrangements are certainly on the table" for the next phase. Nothing has been filed yet.

How a large load actually gets power from Ameren Missouri

This is the part I'd read twice, because it is where land value gets made or lost.

  1. Initial evaluation. Anyone expecting more than 25 MW goes through Ameren's planning process. You give Ameren the load, location and schedule, and it does a high-level screen. No deposit.
  2. Letter of Agreement and queue. A formal study request comes with a $200,000 refundable deposit, topped up in $200,000 steps if costs run over. Queue order is set by the date of complete information and deposit. Ameren studies up to four projects at a time.
  3. Interconnection study. Ameren has described it as typically 120 to 150 days, longer if complex. The resulting plan is good for six months.
  4. Construction agreement. Sets the cost and schedule of the wires, substations and equipment to serve the site. The customer pays for dedicated facilities. It has to be signed inside the six-month window, or the project can go back to the queue.
  5. Electric service agreement. At 75 MW and up, the large-load tariff applies: a 12-year term plus up to five years of ramp, a minimum bill at 80% of contract capacity, collateral equal to two years of minimum bills (with discounts for strong credit), and 24 months' notice to exit.

And the line is long. In testimony this May, Ameren said it had received additional transmission study requests representing about 15.5 GW of new load, on top of what was already signed or under construction agreement.

Illinois is a different road

Ameren Illinois owns wires, not power plants, so supply comes from the market. Its proposed large-load rules, still pending at the Illinois Commerce Commission, would apply above 100 MW and rank the queue by what you can document: site control plus a named end user plus a supply plan goes first. Site control alone goes last. Ameren Illinois reported 850 MW of construction agreements as of the first quarter.

What it means for owners, developers and users

For landowners. Price your land by its stage, not its acreage. Raw land, a queued study request, a completed study, a signed construction agreement and an ESA with a creditworthy user are five very different assets. The real step up is the construction agreement. Before you market on a study, ask Ameren whether it transfers to a buyer. That isn't public.

For developers. File the formal study once you have site control, a defined point of interconnection and a load profile, and can fund a construction agreement within six months of results. Filing earlier mostly buys a queue date with a shelf life. And if the campus will ever pass 75 MW, plan on the large-load tariff from day one. Phasing under the line only works for genuinely small sites.

For users. The new plants are sized for load that has already signed. If you are not in the queue yet, my read is that firm Ameren power for a new large load is more of a 2032 to 2036 conversation. The near-term wins are expansions at signed campuses and the land around them. Bring your credit story early; collateral discounts run on ratings and liquidity.

For everyone. Zoning certainty is worth as much as power position here. The City of St. Charles has permanently banned large data centers, and Troy, Ill., has a moratorium with a 30 MW cap proposed. County versus city lines matter.

My read

  1. The queue is the product. In Ameren territory, the stage a site has reached is worth more than the dirt.
  2. Signed load is covered. The next wave is not. Roughly 3 GW of new nameplate lands in 2027 and 2028, and it is spoken for.
  3. Same playbook as Evergy, different calendar. The study steps and core tariff terms closely mirror Evergy's, so a power-ready packet built for Kansas City works in St. Louis with MISO in place of SPP. Evergy has already filed for nonrefundable advance payments in Kansas. Ameren has only said they're on the table.

Checklist you can reuse

  1. What stage is this site in, and do you have it in writing from Ameren?
  2. When does the study or plan expire?
  3. Will the full campus ever pass 75 MW?
  4. Can the queue position, study or construction agreement be assigned?
  5. Who is the end user or guarantor, and what is their credit?
  6. Is the site in a city or county with a ban, moratorium or cap?

Let's talk

If you own land in Ameren territory, are building there, or need power in Missouri or Metro East in the next five years, I'd like to compare notes. City and county are enough to start, so leave out street addresses and confidential files.

Share a site or requirement

What changed in your underwriting after this call? Hit reply. I read every one.

Subscribe to Speed to Power

Talk soon,

Logan Freeman, Midwest CRE Advisors

Sources

‍

VIEW FULL ARTICLEDOWNLOAD PDF

What's next?

Keep reading our latest market research, get Speed to Power in your inbox, or talk with our team about a property or requirement.